Deal or Case
|
Negotiated, on behalf of a contractor and hospital, the removal and replacement of three 900-ton capacity chillers that failed to perform as warranted
Negotiated, on behalf of a contractor and hospital, the removal and replacement of three 900-ton capacity chillers that failed to perform as warranted; the manufacturer not only paid for the removal of the defective chillers from the hospital, but purchased replacement chillers from a competitor manufacturer. |
|
|